ºúÌÒÅ®Éñ

Roads Capital Programme 2024/25

Mid ºúÌÒÅ®Éñ, Kintyre and the Islands surface dressing and bituminous surfacing schemes 2024/25

Programme status key
Description Status
SCHEME PROGRAMMED TO BE DELIVERED - ( Approximate duration and START month indicated ) Scheduled
SCHEME UNDERWAY - WORK IN PROGRESS -  (Traffic Management as required, during works) In progress
WORKS ONSITE SUBSTANTIALLY COMPLETE. ( Road Markings and White Lining - Weather permitting ) Complete

Last updated - 25th October 2024

Mid ºúÌÒÅ®Éñ

Surface dressing and pre-surface dressing

Mid ºúÌÒÅ®Éñ - surface dressing and pre-surface dressing
Location Treatment type Duration - days Start month Status
C30 Ford - Kilmaha  inc Balure Spur Pre-SD 2024 15 May-24 Complete
C30 Ford - Kilmaha  inc Balure Spur Laying 2024 4 Jul-24 Complete
2025 Pre-SD U18 Drimvore - Crinan ferry - Moss area Pre-SD 2025 20 Jun-24 Complete

Bituminous surfacing etc.

Mid ºúÌÒÅ®Éñ - bituminous surfacing
Location Treatment type Duration - days Start month Status
A819 Electric Cottage  -  PH 4  Widening/Surfacing 150 Sept-24 Complete
B8002  Ardfern to Craignish ( 4 sites = 1815 Lin.m)  Overlay 20 Feb-25 Scheduled
U38 Barmolloch   (Upper  Kilmicheal glen ) Overlay 10 June-24 Complete
 U47 Crinan Loop  inc  Drainage improvements C39 Overlay 15 May-24 Complete
C43-010 Lock 4 Bridge deck  ( Material tbc) Deck surface replace 10 Feb-25 Scheduled

Kintyre

Surface dressing and pre-surface dressing

Kintyre - surface dressing and pre-surface dressing
Location Treatment type Duration - days Start month Status
2024 Pre -SD  U17 Pre-SD 2024 3 May-24 Complete
2024 SD  - U17 A83 - Upperballywilline Laying 2024 2 Jun-24 Complete
2025 Pre-SD    Isle of Gigha  ( whole network) Pre-SD 2025 30 Feb-25 Scheduled

Bituminous surfacing etc.

Kintyre - bituminous surfacing
Location Treatment type Duration - days Start month Status
B842  - Main St to New Quay St Inlay 10 Jun-24 Complete
u15 Crosshill Ave @ Range Rd junction Inlay 10 Aug-24 Complete
Meadows Ave West side Inlay 10 Aug-24 Complete
Tomaig road - Campbeltown  Inlay 10 Aug-24 Complete
B842 Campbeltown Esplanade Inlay 10 Jul-24 Complete
Davaar Ave  - Albyn Ave to Calton hill Inlay 10 Jul-24 Complete
UC09 Calton Ave  - Albyn Ave to Davaar Ave Inlay 10 Jul-24 Complete
Shore St  - Main St to New Quay St Inlay 10 Aug-24 Complete

Islands

Carry over from 2023/24

Islands - carry over from 2023/24
Location Treatment type Duration - days Start month Status
Islay  - A846 - Corrary Hill - Island Ho  ( ferry delay) Overlay   - c/o budget 10 Feb-25 Scheduled
Islay  - C12 - S of Barr to W of Cattadale ( ferry delay) Overlay   - c/o budget 10 Nov-24 Scheduled

Surface dressing preparation

Islands - surface dressing preparation
Location Treatment type Duration - days Start month Status
2025 Pre-SD B8085 & B8086 / U48  Colonsay Pre-SD 2025 15 Jun-24 Complete

Bituminous surfacing etc.

Islands - bituminous surfacing
Location Treatment type Estimated value Duration - days Start month Status
 B8085 Colonsay Overlay &²Ô²ú²õ±è;£48,263.01 10 Jun-24 Complete
 A846 Bunanuisg to Cruach Rd  - Thru' Bowmore Inlay &²Ô²ú²õ±è;£278,801.19 25 Sept-24 Complete
 Uc16 Flora Street Inlay &²Ô²ú²õ±è;£113,456.59 15 Sept-24 Complete
 A847 Bruach Gorm to Sewage Works - Pt Charlotte Inlay / Overlay &²Ô²ú²õ±è;£217,496.79 20 Feb-25 Scheduled
 Uc10 North of Ardnahoe Overlay &²Ô²ú²õ±è;£39,449.94 5 Sept-24 Complete
 A847 Gowanlea to Seaview - Bruichladdich 700linm Inlay / Overlay &²Ô²ú²õ±è;£44,454.46 5 Feb-25 Scheduled
Did you find what you were looking for?

Why wasn't this information helpful

Limit to 250 characters.